Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May.

Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May.

Standard Cost per Unit Actual Cost per Unit
Direct materials:
Standard: 1.80 feet at $2.80 per foot $ 5.04
Actual: 1.75 feet at $3.00 per foot $ 5.25
Direct labor:
Standard: 0.90 hours at $16.00 per hour 14.40
Actual: 0.95 hours at $15.40 per hour 14.63
Variable overhead:
Standard: 0.90 hours at $4.00 per hour 3.60
Actual: 0.95 hours at $3.60 per hour 3.42
Total cost per unit $ 23.04 $ 23.30
Excess of actual cost over standard cost per unit $ 0.26

The production superintendent was pleased when he saw this report and commented: This $0.26 excess cost is well within the 2 percent limit management has set for acceptable variances. It's obvious that there's not much to worry about with this product."

Actual production for the month was 10,000 units. Variable overhead cost is assigned to products on the basis of direct labor-hours. There were no beginning or ending inventories of materials.

image text in transcribed

image text in transcribed

Required: 1. Compute the following variances for a. Materials price and quantity variances. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance).) Materials price variance Materials quantity variance b. Labor rate and efficiency variances. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance).) Labor rate va rance Labor efficiency variance c. Variable overhead rate and efficiency var ances (input all amounts as positive values. Indicate the effect of each variance by selecting for favorable, "U for unfavorable, and one for no effect e zero va ance .) Variable overhead rate variance Variable overhead efficiency variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Irregularities Frauds And The Necessity Of Technical Auditing In Construction Industry

Authors: A. L. M. Ameer

1st Edition

1481799754, 978-1481799751

More Books

Students also viewed these Accounting questions

Question

What is meant by 'Wealth Maximization ' ?

Answered: 1 week ago