La Barte Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used
La Barte Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available:
Quantity of direct labor used 800 hrs.
Actual rate for direct labor $12.50 per hr.
Bicycles completed in July 380 bicycles
Standard direct labor per bicycle 2 hrs.
Standard rate for direct labor $12.80 per hr.
a.Determine the direct labor rate variance, time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct labor rate variance $?
Direct labor time variance $?
Total direct labor cost variance $?
b.How much direct labor should be debited to Work in Process?
$
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started