Lab 2 : Create Work Breakdown Structure ( WBS ) , Project Network Diagram, and High - Level Budget Estimated time needed: 1 3 5
Lab : Create Work Breakdown Structure WBS Project Network Diagram, and HighLevel Budget
Estimated time needed: minutes
Objectives
After completing this lab, you will be able to:
Create a work breakdown structure WBS
Create a project network diagram
Create a highlevel budget using an RBS
Prerequisites
You must have Microsoft Excel installed on your computer or a Microsoft Office account online. If you want to sign up for Microsoft Office online and need help with the steps to sign up click here.
If you are new to Microsoft Excel, click here.
You should have completed the following labs before starting:
Create a project charter
Create a stakeholder register
It is highly recommended that you watch the following videos before starting:
Create a WBS
Create a Network Diagram
Create a HighLevel Budget
Scenario: Develop an Application App to Provide RealTime Marketing Data
Good news! The project charter and stakeholder register have been approved. The Project Management Institute PMI recommends that scope, schedule, and cost be planned in this order during initial baseline planning. Your team will follow this recommendation.
The project charter divided the project into five phases for scheduling purposes. The project team has decided to tailor the work breakdown structure WBS schedule, and highlevel budget estimate using these phases.
The table below identifies each phase and tasks to be considered in the scope, schedule, and cost planning for this project. Note that the key task requirements for the major tasks are not listed in the order in which they will occur. When planning scope, schedule, and cost, your team must determine the task flow.
Project Phase
Design days
Development days
Test days
Key Task Requirements
Gain final design approval
Identify vendor to design and develop app
Solicit initial design feedback
Define key app functionality requirements
Develop initial design
Finalize vendor contract
Update design based on feedback
Perform prototype beta test
Develop an initial prototype
Develop an app launch plan
Update prototype based on feedback
Implement IT upgrades
Solicit beta test feedback
Gain prototype signoff
Test the final app prototype
Begin fullscale development
Begin IT hiring
Gain customer acceptance
Approve the launch plan
Train Marketing personnel on a new app
Exercise : Create a WBS
Keeping the CTRL key pressed, click here to download the WBS Template document.
Note: On Mac systems, keep the COMMAND key pressed instead of the CTRL key.
Keeping the CTRL key pressed, here to download the WBS Example document.
Note: On Mac systems, keep the COMMAND key pressed instead of the CTRL key.
In the WBS template, create the work breakdown structure with at least three levels. Start with the project name, followed by the project phases, and end with the activities.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started