Labor Variances Verde Company produces wheels for bicycles. During the year, 654,000 wheels were produced. The actual labor used was 359,000 hours at $9.00 per hour. Verde has the following labor standards: 1) $10.40 per hour; 2) 0.45 hour per wheel. Required: 1. Compute the labor rate variance. X Favorable 2. Compute the labor efficiency variance. $ X Unfavorable