Lake Construction Co. uses the percentage of completion method for long-term construction contracts. The company has a project with a contract price of P7,000,000, on
Lake Construction Co. uses the percentage of completion method for long-term construction contracts. The
company has a project with a contract price of P7,000,000, on which P600,000 of gross profit has been
recognized in prior years. Information for the current year is as follows:
Total cost incurred through current year
P5,000,000
Estimated cost remaining at the end of the current year
2,800,000
What is the loss that Lake should recognize in the current year?
a.
600,000
b.
800,000
c. 1,400,000
d. 0
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started