Question
Lampost Manufacturing provides the following information: To produce a unit of product: Mixing department 4 minutes per unit Molding department 7 minutes per unit Casting
Lampost Manufacturing provides the following information:
To produce a unit of product:
Mixing department 4 minutes per unit
Molding department 7 minutes per unit
Casting department 9 minutes per unit
Finishing department 5 minutes per unit
There is a wait time of 5 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 8 minutes.
Required:
How long does it take to produce a batch of 20 units under a traditional manufacturing approach? (be sure to show all work)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started