Lead Time iSounds Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit ( PC ) board assembly, final assembly, testing, and shipping. In

Lead Time
iSounds Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed, the operator moves the assembled boards to the final assembly area. This move takes 10 minutes to complete.
The final assembly for each stereo unit requires 19 minutes and is also done in batches of 50 units. A batch of 50 stereos is moved into the test building, which is across the street. The move takes 20 minutes. Before conducting the test, the test equipment must be set up for the particular stereo model. The test setup requires 30 minutes. The units wait while the setup is performed. In the final test, the 50-unit batch is tested one at a time. Each test requires 12 minutes. The completed batch, after all testing, is sent to shipping for packaging and final shipment to customers. A complete batch of 50 units is sent from testing to shipping. The Shipping Department is located next to testing. Thus, there is no move time between these two operations. Packaging and labeling requires 9 minutes per unit.
Required:
1. Determine the amount of value-added and non-value-added lead time and the value-added ratio in this process for an average stereo unit in a batch of 50 units. Categorize the non-value-added time into wait and move time. Round the percentage to one decimal place.
Line Item Description Answer Answer
Value-added lead time fill in the blank 1 min.
Non-value-added lead time:
Wait time lead time fill in the blank 2 min.
Move time lead time fill in the blank 3 min.
Total non-value-added lead time fill in the blank 4 min.
Total lead time fill in the blank 5 min.
Value-added ratio (as a percent) fill in the blank 6%
2. Move time in this process could best be reduced by:
a. Doing nothing.
b. Changing the layout from a process orientation to a product orientation.
c. Increasing batch sizes.
d. Eliminating the testing step.
e. Hiring more workers.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

3rd Edition

0749467223, 978-0749467227

More Books

Students explore these related General Management questions