Lead Time The Swift Mountain Ski Company manufactures skis in the finishing and assembly process. Skis are manufactured in 30-ski batch sizes. The finishing time

Lead Time

The Swift Mountain Ski Company manufactures skis in the finishing and assembly process. Skis are manufactured in 30-ski batch sizes. The finishing time is 14 minutes per ski. The assembly time is 10 minutes per ski. It takes 8 minutes to move a batch of skis from finishing to assembly.

a. Compute the value-added, non-value-added, and total lead time of this process.

Value-added lead time 24 minutes CORRECT
Non-value-added lead time minutes
Total lead time minutes

b. Compute the value-added ratio. Round to one decimal place. %

Feedback

a. Recall that lead time can be classified as one of the following: 1. Value-added lead time, which is the time spent in converting raw materials into a finished unit of product. 2. Non-value-added lead time, which is the time spent while the unit of product is waiting to enter the next production process or is moved from one process to another. In this exercise: Value-added lead time = Finishing time + Assembly time Non-value-added lead time = Total within-batch wait time + Move time, where Total Within-Batch Wait Time = (Total Time to Perform Operations) x (Batch Size - 1) Add value-added lead time + non-value-added lead time to obtain total lead time.

b. Calculate Value-Added Ratio = Value-Added Lead Time Total Lead Time

Learning Objective 1.image text in transcribed

Lead Time The Swift Mountain Ski Company manufactures skis in the finishing and assembly process. Skis are manufactured in 30-ski batch sizes. The finishing time is 14 minutes ski. The assembly time is 10 minutes per ski. It takes 8 minutes to move a batch of skis from finishing to assembly. a. Compute the value-added, non-value-added, and total lead time of this process. Value-added lead time 24 minutes Non-value-added lead time 15 x minutes 43 x minutes Total lead time b. Compute the value-added ratio. Round to one decimal place. 65.12 X Feedback Check My Work a. Recall that lead time can be classified as one of the following: 1. Value-added lead time, which is the time spent in converting raw materials into a finished unit of product. 2. Non-value-added lead time, which is the time spent while the unit of product is waiting to enter the next production process or is moved from one process to another. In this exercise: Value-added lead time E Finishing time Assembly time Add value-added lead time non-value-added lead time to obtain total lead time. b. Calculate Value-Added Ratio Value-Added LeadTime Total Lead Time Learning objective 1

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

My Favorite Auditor Gave Me This Book

Authors: Funny Planner Publishing

1st Edition

1676058060, 978-1676058069

More Books

Students also viewed these Accounting questions

Question

What are the objectives of job evaluation ?

Answered: 1 week ago

Question

Write a note on job design.

Answered: 1 week ago

Question

Compute the derivative of f(x)cos(-4/5x)

Answered: 1 week ago

Question

Discuss the process involved in selection.

Answered: 1 week ago