Leah is the project manager of a project. She, along with her team, is planning responses to a set of risks. As a direct result
Leah is the project manager of a project. She, along with her team, is planning responses to a set of risks. As a direct result of implementing these risk responses, she anticipates certain other risks to arise. What are these new risks called? Select one: a. Secondary risks b. Risidual Risks c. Contingent Risks d. Permanent Risk