Leila is estimating a task duration and she has got an optimistic duration of 18 days, a pessimistic duration of 36 days, and a most

Leila is estimating a task duration and she has got an optimistic duration of 18 days, a pessimistic duration of 36 days, and a most likely duration of 24 days. What is the standard deviation of the e

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions