Leon Companys city center plant recently hired a second shift of employees who manufacture the product Plumbo. (The second shift works from 4 p.m. to

Leon Companys city center plant recently hired a second shift of employees who manufacture the product Plumbo. (The second shift works from 4 p.m. to midnight after the first shift is finished, which doubles the total plant capacity.) Information about the cost of labour in the previous month is as follows:

Standard Actual (1,000 units produced)
Hours 3.0 hrs/unit 2,500 hours
Rate $26/hr $75,300

The labour efficiency variance at the city center plant in the previous month was (determine also wether it is favourable or unfavourable):

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting In Business

Authors: R. J. Bull

5th Edition

0408014865, 978-0408014861

More Books

Students also viewed these Accounting questions

Question

which if the following ckncerning MRP II is flase

Answered: 1 week ago