Leonard purchased an unconstructed condominium in a large development. The contract stated that delivery of the completed condo was to be on a date set
Leonard purchased an unconstructed condominium in a large development. The contract
stated that delivery of the completed condo was to be on a date set by the developer before
February 1, 2010. Construction proceeded on schedule except on April 25, 2009, the whole
development burned to the ground. After spending some time looking for the cause of the
fire, the developer started the process of rebuilding in October 2009. It looks like the condo
will be delivered about a year later than originally anticipated. Is Leonard bound by the
contract under these circumstances? Does it matter if the fire was caused by the developer's
negligence?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started