Let s consider an assembly line that runs two shifts per day, where each shift runs 8 hours. Each shift has 3 5 minutes lunch
Lets consider an assembly line that runs two shifts per day, where each shift runs hours. Each shift has minutes lunchdinner and minutes for tea break. Note that the assembly line does not run during the lunch break and lunchdinner Lets assume that the customer demand is units per day and manufacturer is capable of producing units per shift.
a Calculate the takt time.
b Does the manufacturer need to reduce the cycle time of product? Why? points
Step by Step Solution
There are 3 Steps involved in it
Step: 1