Let s consider an assembly line that runs two shifts per day, where each shift runs 8 hours. Each shift has 3 5 minutes lunch

Lets consider an assembly line that runs two shifts per day, where each shift runs 8 hours. Each shift has 35 minutes lunch/dinner and 20 minutes for tea break. Note that the assembly line does not run during the lunch break and lunch/dinner. Lets assume that the customer demand is 80 units per day and manufacturer is capable of producing 35 units per shift.
a) Calculate the takt time.
b) Does the manufacturer need to reduce the cycle time of product? Why? (1.25 points

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring Management

Authors: John R. Schermerhorn

3rd edition

1118217252, 9780470878217, 978-1118217252

More Books

Students also viewed these General Management questions

Question

The dark side of leadership.

Answered: 1 week ago