Question

1 Approved Answer

LevelUp Construction is working on a contract to construct a large building. The value of the contract is $1,725,500. The controller of LevelUp, Ernie Carlos,

LevelUp Construction is working on a contract to construct a large building. The value of the contract is $1,725,500. The controller of LevelUp, Ernie Carlos, wants to know how effective the company has been in their construction over the last 3 years. Looking through the financial records of the company, Ernie finds the following information:

2017 2018 2019 Total
Gross Profit (loss) 76,525 145,250 (22,500) 199,275
Costs Incurred 365,000 325,475 835,750 1,526,225

Instructions:

Help Ernie determine the following:

1. How much costs were incurred during 2018:-

2. What percentage of the project was completed at the end of 2018:-

3. What was the total estimated gross profit for the building project at the end of 2018.

4. What was the estimated to cost to complete the project at the end of 2018.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Reporting And Analysis

Authors: John Dunn, Margaret Stewart

1st Edition

0470973609, 9780470973608

More Books

Students also viewed these Accounting questions