Question
Lido Company's standard and actual costs for the most recent period, are given be- low: - 2,600 metres of material were purchased at $1.25 per
Lido Company's standard and actual costs for the most recent period, are given be-
low:
- 2,600 metres of material were purchased at $1.25 per metre, and 2,000 metres
were used,
- 1,420 hours oflabour were assigned to produce 950 units. Direct labour actual hourly rate was $16.65
- Actual Variable manufacturing overhead amounted to $3.70 per labour hour. Lido uses direct labour hours as the cost driver for overheadapplication. Total Actual Fixed Overhead amounted to $11,500 for the period
Lido used the following manufacturing standards Per Unit:
* Direct Material: 2metres @$1.50 per metre
* Direct Labour : 1.25Hours @ $16.00per hour
* MOH - Variable: 1.25Hours @ $3.50 per DLH
- Fixed: 1.25 Hrs @$10.00 based on capacity to produce 1,000 units
Required:
From the above information, compute the variances necessary to complete the following Variance Report. In the analysis section of the report, identify any exceptions and make recommendations based on your analysis. Provide the journal entries for direct materials and direct labour only.
Inputs: DM Outputs:950 units
Materials STD:2m @ $1.50 per m
AQ x AP AQ x SP SQ x SP
2,500m 2,500m
AQU x SP
Journal Entries:
Purchase:
Use:
Input: Output:950 units
Direct Labour STD: 1.25H @ $16.00 per hr
AH x AR AH x SR SH x SR
1,420 H 1,420H
Journal Entries:
Purchase:
Use:
Manufacturing Overhead : Variable Costs
Input: STD: 1.25H @ $3. 50per DLH Output: 950 units
AH x AR AH x SR SH xSR
1,420H x 1,420H x
Fixed:
Actual Budget Applied
$11,500 $12,500
Variance Analysis and Report
Variances F U
Direct Materials: - Price
- Quantity
Direct Labour - Rate
-Efficiency
Overhead - Variable: - Spending
- Efficiency
Fixed: - Budget
- Volume
Totals:
WHO? WHAT? WHY? Analysis(briefly):
Identify any exceptions from the above, and explain why you consider them important.
Comment on the exceptions you have identified: Which variances will you seek more information on? Why?
Who are the managers you will address in order to get answers?: What information will you be looking for? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started