Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Standard Actual
Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: | |||||||||
Standard | Actual | ||||||||
Materials: | |||||||||
Standard: 2 metres at $1.50 per m. | $3.00 | ||||||||
Actual: 2.1 metres at $1.60 per m. | $3.36 | ||||||||
Direct Labour: | |||||||||
Standard: 1.5 hours at $6.00 per hr. | $9.00 | ||||||||
Actual: 1.4 hours at $6.50 per hr. | $9.10 | ||||||||
Variable overhead: | |||||||||
Standard: 1.5 hours at $3.40 per hr. | $5.10 | ||||||||
Actual: 1.4 hours at $3.10 per hr. | $4.34 | ||||||||
Total Unit Cost: | $17.10 | $16.80 | |||||||
There were no inventory of materials at the beginning or end of the period. | |||||||||
Required: | |||||||||
(a) | Materials price variance | ||||||||
(b) | Materials quantity variance | ||||||||
(c) | Direct labour rate variance | ||||||||
(d) | Direct labour efficiency variance | ||||||||
(e) | Variable overhead spending variance | ||||||||
(f) | Variable overhead efficiency variance |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started