Question

1 Approved Answer

Listed in the below table are the tasks and times for a product development project. Expected time in weeks, variance of the expected time in

Listed in the below table are the tasks and times for a product development project.

image text in transcribed

Expected time in weeks, variance of the expected time in square weeks, and probability that this project is completed in a year are.

\begin{tabular}{|l|l|l|l|l|} \hline Activity & Predecessoractivities & Optimistictime,weeks & Mostlikelytime,weeks & Pessimistictime,weeks \\ \hline A & - & 10 & 12 & 14 \\ \hline B & - & 12 & 21 & 36 \\ \hline C & A & 12 & 13.5 & 18 \\ \hline D & B & 16 & 24 & 38 \\ \hline E & C & 12 & 18 & 10 \\ \hline Finish & E & 2 & 6 & \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Principles

Authors: Jerry J. Weygandt, Valerie A. Kinnear, Donald E. Kieso, Paul D. Kimmel, Barbara A. Trenholm, Joan E. Barlow

6th Canadian Edition

1118557301, 978-1118557303

More Books

Students also viewed these Accounting questions

Question

=+Could you create an interactive game on the website?

Answered: 1 week ago