Answered step by step
Verified Expert Solution
Question
1 Approved Answer
. ll chatr 11:22 PM 33% 3011 project management Group a... Group assignment 3 Commonwealth Stadium A bid to build the new 56,000 seat Commonwealth
. ll chatr 11:22 PM 33% 3011 project management Group a... Group assignment 3 Commonwealth Stadium A bid to build the new 56,000 seat Commonwealth Stadium in Toronto Must start September 4, 2021 Complete: 2024 for the commonwealth games - A penalty of $100K/day of delay before Jun 1", 2024 Net: $2M Part 2: Bolton Construction wins the bid for the stadium FIFA World Cup is on May 1", 2024 Offering a bonus payment of $20k/day Net: $2M on the original project Task: 1) Crash the project using the Crash Cost and Crash time 2) Answer the question: - Will the project finish by May 1", 2024? - Will they make or lose money? - The least cost solution to get the stadium complete by May 1", 24? - The new Critical Path(s) CRASH COST and CRASH TIME (possibilities) DESCRIPTION Normal Time Crash Time Crash cost Drive support piling 120 days 103 days $5000/day Pour main concourse 120 days 110 days $3000/day Construct upper steel bowl 120 days 100 days $3000/day Install seats 140 days 119 days $1500/day Install Jumbo Scoreboard 30 days 21 days $7500/day Stadium infrastructure 120 days 90 days $2000/day Construct steel canopy 75 days 41 days $2500/day Construct roof 180 days 125 days $2000/day Technical Detail Descrintion. No A B U D E F 6 I G H 1 ] L M Description Duration (days) Predecessor Clear the site 70 NONE Demolish an adjacent building 20 A Set up the construction site 50 B Create a temporary warehouse 30 Drive support pilings 120 Pour the lower concrete bowl 120 E Pour the main concourse 120 CF Install the playing field 90 C,F Construct the upper steel bowl 120 CF Install the seats 140 D,G,1 Build the luxury boxes 90 D,G,1 Install the Jumbo Scoreboard 30 D,G,1 Install the stadium infrastructure 120 D,G,1 Construct the steel canopy 75 J Install the lighting and sound systen 30 N,D Build the roof track support 80 F Conform the dimensions of the roof 10 P Build the roof at a separate site 180 Q Truck the roof 5 5 R Install the roof track 90 P Install the roof 90 ST Inspection 20 H,K,L,M,O,U N z oo P Q R S T T U V . ll chatr 11:22 PM 33% 3011 project management Group a... Group assignment 3 Commonwealth Stadium A bid to build the new 56,000 seat Commonwealth Stadium in Toronto Must start September 4, 2021 Complete: 2024 for the commonwealth games - A penalty of $100K/day of delay before Jun 1", 2024 Net: $2M Part 2: Bolton Construction wins the bid for the stadium FIFA World Cup is on May 1", 2024 Offering a bonus payment of $20k/day Net: $2M on the original project Task: 1) Crash the project using the Crash Cost and Crash time 2) Answer the question: - Will the project finish by May 1", 2024? - Will they make or lose money? - The least cost solution to get the stadium complete by May 1", 24? - The new Critical Path(s) CRASH COST and CRASH TIME (possibilities) DESCRIPTION Normal Time Crash Time Crash cost Drive support piling 120 days 103 days $5000/day Pour main concourse 120 days 110 days $3000/day Construct upper steel bowl 120 days 100 days $3000/day Install seats 140 days 119 days $1500/day Install Jumbo Scoreboard 30 days 21 days $7500/day Stadium infrastructure 120 days 90 days $2000/day Construct steel canopy 75 days 41 days $2500/day Construct roof 180 days 125 days $2000/day Technical Detail Descrintion. No A B U D E F 6 I G H 1 ] L M Description Duration (days) Predecessor Clear the site 70 NONE Demolish an adjacent building 20 A Set up the construction site 50 B Create a temporary warehouse 30 Drive support pilings 120 Pour the lower concrete bowl 120 E Pour the main concourse 120 CF Install the playing field 90 C,F Construct the upper steel bowl 120 CF Install the seats 140 D,G,1 Build the luxury boxes 90 D,G,1 Install the Jumbo Scoreboard 30 D,G,1 Install the stadium infrastructure 120 D,G,1 Construct the steel canopy 75 J Install the lighting and sound systen 30 N,D Build the roof track support 80 F Conform the dimensions of the roof 10 P Build the roof at a separate site 180 Q Truck the roof 5 5 R Install the roof track 90 P Install the roof 90 ST Inspection 20 H,K,L,M,O,U N z oo P Q R S T T U V
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started