LO.4 (Comprehensive) Birmingham Contractors uses a job order costing system. In May 2010, the company made a $3,300,000 bid to build a pedestrian overpass over
LO.4 (Comprehensive) Birmingham Contractors uses a job order costing system. In
May 2010, the company made a $3,300,000 bid to build a pedestrian overpass over the
beach highway at Gulf Shores, Alabama. Birmingham Contractors won the bid and
assigned #515 to the project. Its completion date was set at December 15, 2010. Th e
following costs were estimated for completion of the overpass: $1,240,000 for direct
material, $670,000 for direct labor, and $402,000 for overhead.
During July, work began on job #515; direct material cost assigned to Job #515
was $121,800, and direct labor cost associated with it was $175,040. The rm uses a
predetermined OH rate of 60 percent of direct labor cost. Birmingham Contractors
also worked on several other jobs during July and incurred the following costs:
Direct material (including Job #515) issued $579,300
Direct labor (including Job #515) accrued 584,000
Indirect labor accrued 55,800
Administrative salaries and wages accrued 39,600
Depreciation on construction equipment 26,400
Depreciation on offi ce equipment 7,800
Client entertainment (on accounts payable) 11,100
Advertising for fi rm (paid in cash) 6,600
Indirect material (from supplies inventory) 18,600
Miscellaneous expenses (design-related; to be paid in the following month) 10,200
Accrued utilities (for offi ce, $1,800; for construction, $5,400) 7,200
During July, Birmingham Contractors completed several jobs that had been in process
before the beginning of the month. Th ese completed jobs sold for $1,224,000 and
payment will be made to the company in August. Th e related job cost sheets showed
costs associated with those jobs of $829,000. At the beginning of July, Birmingham
Contractors had Work in Process Inventory of $871,800.
a. Prepare a job order cost sheet for Job #515, including all job details, and post the
appropriate cost information for July.
b. Prepare journal entries for the preceding information.
c. Prepare a Cost of Goods Manufactured Schedule for July for Birmingham
Contractors.
d. Assuming that the company pays income tax at a 40 percent rate, prepare an income
statement for Birmingham Contractors.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started