(Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000.

(Long-Term Contract with Interim Loss)

On May 1, 2020, Jackson Construction Company contracted to

construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual

contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022

are

given below.

2020

2021

2022

Contract costs incurred during the year

$3,400,000

$2,400,000

$2,900,000

Estimated costs to complete the contract at 12/31

4,600,000

3,100,000

-0-

Billings

1,200,000 4,100,000 4,300,000

Instructions

(a)

Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a

result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)

(b)

Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of

this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore incomes taxes.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advances In Quantitative Analysis Of Finance And Accounting (Vol. 4)

Authors: Lee Cheng Few

2nd Edition

9812700218, 9789812700216

More Books

Students also viewed these Accounting questions