Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Looking at types of networks, what type tends to be used for R & D projects where the risks in calculating time durations have a

Looking at types of networks, what type tends to be used for R & D projects where the risks in calculating time durations have a high variability?

Select one:

CPM

Gantt

PDM

ADM

PERT

Clear my choiceQuestion 2Not yet answeredPoints out of 5.00Flag questionQuestion text

The major disadvantage of a bar chart is:

Select one:

Lack of time-phasing

Cannot be related to calendar dates

Does not show activity interrelationships

Cannot be related to labor planning

Cannot be related to cost estimates

Clear my choiceQuestion 3Not yet answeredPoints out of 5.00Flag questionQuestion text

Line of balance charts are used most frequently in:

Select one:

Engineering

Marketing

Manufacturing

Accounting

Contracts and procurement

Clear my choiceQuestion 4Not yet answeredPoints out of 5.00Flag questionQuestion text

The utility of network-based schedules:

Select one:

Reveals interdependencies

Facilitates "what if" exercises

They identify the longest path or critical paths

Provides information on resource requirements, time requirements, and trade-offs.

All of the above

Clear my choiceQuestion 5Not yet answeredPoints out of 5.00Flag questionQuestion text

In the PDM, common constraints include:

Select one:

Start-to-start

Finish-to-start

Finish-to-finish

2 and 3 only

1, 2 and 3

Clear my choiceQuestion 6Not yet answeredPoints out of 5.00Flag questionQuestion text

Smoothing out resource requirements from period to period is called resource _____________.

Select one:

Allocation

Partitioning

Leveling

Quantification

None of the above

Clear my choiceQuestion 7Not yet answeredPoints out of 5.00Flag questionQuestion text

In PERT, the probabililty distribution of time required for an activity uses a ______________________ distribution.

Select one:

Normal

Poisson

Lambda

Gamma

Beta

Clear my choiceQuestion 8Not yet answeredPoints out of 5.00Flag questionQuestion text

Based upon the situation, which method(s) shown below could be accceptable for reducing cost or shortening the schedule?

Select one:

Crashing

Changing scope

Performing activities in parallel rather than in series

All of the above

1 and 3 only

Clear my choiceQuestion 9Not yet answeredPoints out of 5.00Flag questionQuestion text

In setting up network schedules, __________________ for an activity equals latest finish minus earliest start minus duration.

Select one:

Minimum Float

Maximum float

Critical Path

Cost of crashing

None of the above.

Clear my choiceQuestion 10Not yet answeredPoints out of 5.00Flag questionQuestion text

The major difference between PERT and CPM networks is:

Select one:

PERT requires three time estimates whereas CPM requires one time estimate

PERT is used for construction projects whereas CPM is used for R & D.

PERT addresses only time whereas CPM also includes cost and resource availability

PERT requires computer solutions whereas CPM is a manual technique

PERT is measured in days whereas CPM uses weeks or months

Clear my choiceQuestion 11Not yet answeredPoints out of 5.00Flag questionQuestion text

Planning activities such that predetermined resource availability pools are not exceeded is called:

Select one:

Resource leveling

Labor leveling

Resource-limited planning

Labor planning

Labor contingency planning

Clear my choiceQuestion 12Not yet answeredPoints out of 5.00Flag questionQuestion text

The critical path in a network is the path that:

Select one:

Has the greatest degree of risk

is the longest path through the network and determines the duration.

Must be completed before all other paths

All of the above

1 and 2 only

Clear my choiceQuestion 13Not yet answeredPoints out of 5.00Flag questionQuestion text

Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the ____________ and identification of the _________________.

Select one:

Slack for each activity, critical path

Slack for each activity, degree of risk for activities

Labor overages, high-risk activities

High-risk activities, contingency plans

Labor availability, contingency plans

Clear my choiceQuestion 14Not yet answeredPoints out of 5.00Flag questionQuestion text

A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from five to eight. This will result in:

Select one:

A shortening of the critical path

A shortening of the noncritical paths

A decrease in the total cost of the project

An increase in the total cost of the project

All are possible based upon where the resources are deployed

Clear my choiceQuestion 15Not yet answeredPoints out of 5.00Flag questionQuestion text

Management has decided to crash a project in order to avoid penalty payments for late deliveries. Additional costs are expected. To crash the project, either overtime or additional resources should be assigned to:

Select one:

All activities

Only those activities with the longest time durations

Those activities on the critical path

Those activities with the greatest degree of risk

None of the above

Clear my choiceQuestion 16Not yet answeredPoints out of 5.00Flag questionQuestion text

A line manager provides you with three estimates for his activity in your PERT network. His estimates are two weeks optimistically, four weeks most likely, and twelve weeks pessimistically. The expected time that would appear on the chart would be:

Select one:

Four weeks

Five weeks

Six weeks

Seven weeks

None of the above

Clear my choiceQuestion 17Not yet answeredPoints out of 5.00Flag questionQuestion text

Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

Select one:

The project manager and project office personnel

The project team and functional managers

The project sponsor

All of the above

1 and 2 only

Clear my choiceQuestion 18Not yet answeredPoints out of 5.00Flag questionQuestion text

In understanding networks, it's helpful to know certain terms. What is the term that describes something "...that is equivalent to a milestone indicating when an activity starts or finishes."

Select one:

Activity

Event

Effort

Duration

Critical Path

Clear my choiceQuestion 19Not yet answeredPoints out of 5.00Flag questionQuestion text

In the construction of a PERT Network, functional managers must submit their estimates using which assumption(s)

Select one:

Optimistic completion time.

Pessimistic completion time.

Most likely completion time.

All of the above.

None of the above.

Clear my choiceQuestion 20Not yet answeredPoints out of 5.00Flag questionQuestion text

PERT and CPM vary in several respects. The text suggests one is that PERT is __________________ oriented and CPM is ____________________ oriented.

Select one:

Progress, Achievement

Activity, Event

Event, Activity

Labor, Capital

None of the above.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

12th Edition

1119165350, 9781119165354

More Books

Students also viewed these General Management questions