Question
Looking at types of networks, what type tends to be used for R & D projects where the risks in calculating time durations have a
Looking at types of networks, what type tends to be used for R & D projects where the risks in calculating time durations have a high variability?
Select one:
CPM
Gantt
PDM
ADM
PERT
Clear my choiceQuestion 2Not yet answeredPoints out of 5.00Flag questionQuestion text
The major disadvantage of a bar chart is:
Select one:
Lack of time-phasing
Cannot be related to calendar dates
Does not show activity interrelationships
Cannot be related to labor planning
Cannot be related to cost estimates
Clear my choiceQuestion 3Not yet answeredPoints out of 5.00Flag questionQuestion text
Line of balance charts are used most frequently in:
Select one:
Engineering
Marketing
Manufacturing
Accounting
Contracts and procurement
Clear my choiceQuestion 4Not yet answeredPoints out of 5.00Flag questionQuestion text
The utility of network-based schedules:
Select one:
Reveals interdependencies
Facilitates "what if" exercises
They identify the longest path or critical paths
Provides information on resource requirements, time requirements, and trade-offs.
All of the above
Clear my choiceQuestion 5Not yet answeredPoints out of 5.00Flag questionQuestion text
In the PDM, common constraints include:
Select one:
Start-to-start
Finish-to-start
Finish-to-finish
2 and 3 only
1, 2 and 3
Clear my choiceQuestion 6Not yet answeredPoints out of 5.00Flag questionQuestion text
Smoothing out resource requirements from period to period is called resource _____________.
Select one:
Allocation
Partitioning
Leveling
Quantification
None of the above
Clear my choiceQuestion 7Not yet answeredPoints out of 5.00Flag questionQuestion text
In PERT, the probabililty distribution of time required for an activity uses a ______________________ distribution.
Select one:
Normal
Poisson
Lambda
Gamma
Beta
Clear my choiceQuestion 8Not yet answeredPoints out of 5.00Flag questionQuestion text
Based upon the situation, which method(s) shown below could be accceptable for reducing cost or shortening the schedule?
Select one:
Crashing
Changing scope
Performing activities in parallel rather than in series
All of the above
1 and 3 only
Clear my choiceQuestion 9Not yet answeredPoints out of 5.00Flag questionQuestion text
In setting up network schedules, __________________ for an activity equals latest finish minus earliest start minus duration.
Select one:
Minimum Float
Maximum float
Critical Path
Cost of crashing
None of the above.
Clear my choiceQuestion 10Not yet answeredPoints out of 5.00Flag questionQuestion text
The major difference between PERT and CPM networks is:
Select one:
PERT requires three time estimates whereas CPM requires one time estimate
PERT is used for construction projects whereas CPM is used for R & D.
PERT addresses only time whereas CPM also includes cost and resource availability
PERT requires computer solutions whereas CPM is a manual technique
PERT is measured in days whereas CPM uses weeks or months
Clear my choiceQuestion 11Not yet answeredPoints out of 5.00Flag questionQuestion text
Planning activities such that predetermined resource availability pools are not exceeded is called:
Select one:
Resource leveling
Labor leveling
Resource-limited planning
Labor planning
Labor contingency planning
Clear my choiceQuestion 12Not yet answeredPoints out of 5.00Flag questionQuestion text
The critical path in a network is the path that:
Select one:
Has the greatest degree of risk
is the longest path through the network and determines the duration.
Must be completed before all other paths
All of the above
1 and 2 only
Clear my choiceQuestion 13Not yet answeredPoints out of 5.00Flag questionQuestion text
Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the ____________ and identification of the _________________.
Select one:
Slack for each activity, critical path
Slack for each activity, degree of risk for activities
Labor overages, high-risk activities
High-risk activities, contingency plans
Labor availability, contingency plans
Clear my choiceQuestion 14Not yet answeredPoints out of 5.00Flag questionQuestion text
A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from five to eight. This will result in:
Select one:
A shortening of the critical path
A shortening of the noncritical paths
A decrease in the total cost of the project
An increase in the total cost of the project
All are possible based upon where the resources are deployed
Clear my choiceQuestion 15Not yet answeredPoints out of 5.00Flag questionQuestion text
Management has decided to crash a project in order to avoid penalty payments for late deliveries. Additional costs are expected. To crash the project, either overtime or additional resources should be assigned to:
Select one:
All activities
Only those activities with the longest time durations
Those activities on the critical path
Those activities with the greatest degree of risk
None of the above
Clear my choiceQuestion 16Not yet answeredPoints out of 5.00Flag questionQuestion text
A line manager provides you with three estimates for his activity in your PERT network. His estimates are two weeks optimistically, four weeks most likely, and twelve weeks pessimistically. The expected time that would appear on the chart would be:
Select one:
Four weeks
Five weeks
Six weeks
Seven weeks
None of the above
Clear my choiceQuestion 17Not yet answeredPoints out of 5.00Flag questionQuestion text
Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:
Select one:
The project manager and project office personnel
The project team and functional managers
The project sponsor
All of the above
1 and 2 only
Clear my choiceQuestion 18Not yet answeredPoints out of 5.00Flag questionQuestion text
In understanding networks, it's helpful to know certain terms. What is the term that describes something "...that is equivalent to a milestone indicating when an activity starts or finishes."
Select one:
Activity
Event
Effort
Duration
Critical Path
Clear my choiceQuestion 19Not yet answeredPoints out of 5.00Flag questionQuestion text
In the construction of a PERT Network, functional managers must submit their estimates using which assumption(s)
Select one:
Optimistic completion time.
Pessimistic completion time.
Most likely completion time.
All of the above.
None of the above.
Clear my choiceQuestion 20Not yet answeredPoints out of 5.00Flag questionQuestion text
PERT and CPM vary in several respects. The text suggests one is that PERT is __________________ oriented and CPM is ____________________ oriented.
Select one:
Progress, Achievement
Activity, Event
Event, Activity
Labor, Capital
None of the above.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started