Looking for the ABC Overhead Calculation of the following problem Direct materials 325,650 Materials handling 35,150 Assembly
Fantastic news! We've Found the answer you've been seeking!
Question:
Looking for the ABC Overhead Calculation of the following problem
Direct materials | 325,650 | |
Materials handling | 35,150 | |
Assembly | 58,025 | |
Setup | 13,450 | |
Product Testing | 3,550 | |
Overhead | 15,890 | |
Output | 41,500 | units |
Direct Labor Hours | 3,650 | |
Setups | 425 | |
Product tests | 70,500 | |
Each unit requires two machine hours | ||
Materials handling based on direct material cost | ||
Product testing based on number of tests | ||
Overhead based on machine hours | ||
Assembly based on direct labor hours | ||
Setups based on the number of setups | ||
Job 153: | ||
Completed | 1,890 | units |
Direct Materials | 12,450 | |
Direct labor hours | 85 | |
Setups | 6 | |
Tests | 2,585 | |