Question
Loreto Statuary manufactures bust statues of famous historical figures. All statues are the same size. Each unit requires the same amount of resources. The following
Loreto Statuary manufactures bust statues of famous historical figures. All statues are the same size. Each unit requires the same amount of resources. The following information is from the static budget for 2017:
Standard quantities, standard prices, and standard unit costs follow for direct materials and direct manufacturing labor:
Read the requirements 3.
Requirement 1. Calculate the sales-volume variance and flexible-budget variance for operating income.
Begin with the actual results, then complete the flexible budget columns and the static budget columns. Label each variance as favorable (F) or unfavorable (U). (For variances with a $0 balance, make sure to enter "0" in the appropriate field. If the variance is zero, do not select a label.)
| Actual |
| Results |
Output units |
|
Revenues |
|
| |
Direct materials |
|
Direct manufacturing labor |
|
Fixed costs |
|
Total costs |
|
Operating income |
|
Flexible-Budget | Flexible | |
Variance | Budget | |
| (1) |
|
| (2) |
|
|
| |
| (3) |
|
| (4) |
|
| (5) |
|
| (6) |
|
| (7) |
|
Sales-Volume | Static | |
Variance | Budget | |
| (8) |
|
| (9) |
|
|
| |
| (10) |
|
| (11) |
|
| (12) |
|
| (13) |
|
| (14) |
|
Requirement 2. Compute price and efficiency variances for direct materials and direct manufacturing labor.
Compute the price and efficiency variances for direct materials. Label each variance as favorable (F) or unfavorable (U).
Price variance |
| (15) |
Efficiency variance |
| (16) |
Compute the price and efficiency variances for direct manufacturing labor. Label each variance as favorable (F) or unfavorable (U).
Price variance |
| (17) |
Efficiency variance |
| (18) |
1: Data Table
Expected production and sales | 6,400 | units |
Expected selling price per unit | $775 | |
Total fixed costs | $1,300,000 |
2: Data Table
| Standard Quantity | Standard Price | Standard Unit Cost |
Direct materials | 15 pounds | $10 per pound | $150 |
Direct manufacturing labor | 3.3 hours | $50 per hour | $165 |
During 2017, actual number of units produced and sold was 4,900, at an average selling price of $800. Actual cost of direct materials used was $743,750, based on 62,500 pounds purchased at $11.90 per pound. Direct manufacturing labor-hours actually used were 19,500, at the rate of $41.00 per hour. As a result, actual direct manufacturing labor costs were $799,500. Actual fixed costs were $1,210,000. There were no beginning or ending inventories.
3: Requirements
1. | Calculate the sales-volume variance and flexible-budget variance for operating income. |
2. | Compute price and efficiency variances for direct materials and direct manufacturing labor. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started