Lowder Inc. builds custom conveyor systems for warehouses and distribution centers. During the month of July, the following occurred: Jul. 1 Purchased materials on account
Lowder Inc. builds custom conveyor systems for warehouses and distribution centers. During the month of July, the following occurred:
Jul. | 1 | Purchased materials on account for $42,630. |
2 | Requisitioned materials totaling $27,000 for use in production: $12,500 for Job 703 and the remainder for Job 704. | |
28 | Recorded direct labor payroll for the month of $26,320 with an average wage of $14 per hour. Job 703 required 780 direct labor hours; Job 704 required 1,100 direct labor hours. | |
28 | Incurred and paid actual overhead of $19,950. | |
28 | Charged overhead to production at the rate of $10 per direct labor hour. | |
30 | Completed Job 703 and transferred it to Finished Goods. | |
31 | Kept Job 704, which was started during July, in process at the end of the month. | |
31 | Sold Job 700, which had been completed in May, on account for cost plus 30%. |
Beginning balances as of July 1 were:
Raw Materials | $6,070 |
Work in Process (for Job 703) | 10,000 |
Finished Goods (for Job 700) | 6,240 |
Required: | |
1. | Prepare the journal entries for July 1 through 28. |
2. | Prepare simple job-order cost sheets for Jobs 703 and 704. |
3. | Prepare the journal entries for events on July 30 and 31. |
4. | Calculate the ending balances of the following: (a) Raw Materials, (b) Work in Process, and (c) Finished Goods. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started