LT Construction Contract: Use the following data for problems # 1 1 - 1 2 The Hi - End Construction Company entered into contracts for
LT Construction Contract: Use the following data for problems #
The HiEnd Construction Company entered into contracts for two separate projects as follows:
The Project AA contract price was $ and provided for penalties of $ per week for late completion. Project AA was completed during Year but the project was four weeks late at completion.
The Project BB contract price was $ Change orders during year added $ to the original contract price. Also, in year the estimated total cost was revised upward by $ie the estimated of total cost was increased
Note: Project AA was completed at end of Year while ProjectBB was still ongoing at end of Yr
The percentageofcompletion method is used for financial reporting purposes. The following data pertains to the separate longterm construction projects in progress:
Project AA Project BB
As of December Year
Cost Incurred to Date $ $
Estimated Cost to Complete $ $
Billings $ $
Cash Collections $ $
As of December Year
Cost Incurred to Date $ $
Estimated Cost to Complete $ $
Billings $ $
Cash Collections $ $
Required: Calculate the Gross ProfitLoss recognized for Year & Year
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started