Lucy is in charge of planning and coordinating a project. Following is the activity information for this project. Time(weeks) Activity Preceded By Optimistic Most Likely

Lucy is in charge of planning and coordinating a project. Following is the

activity information for this project.

Time (weeks)

Activity Preceded By Optimistic Most Likely Pessimistic

A -- 2 2 4

B A 8 12 16

C A 4 8 12

D B,C 2 4 6

E B 4 6 8

F A 2 4 6

G D 2 4 6

H G 2 4 6

I E,F,H 2 2 2

Requested:

(a) Construct a precedence diagram.

(b) Identify the Critical Path(s) and the expected completion time.

(c) What is the probability that the training program can be completed in 26 

weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Corporate Finance

Authors: Stephen A. Ross, Randolph W. Westerfield, Bradford D.Jordan

8th Edition

978-0073530628, 978-0077861629

More Books

Students also viewed these Corporate Finance questions