Lucy is managing a complex design-and-build project. Stakeholder involvement and influence have been significant since the project's inception. Under such circumstances, the monitoring the stakeholder
Lucy is managing a complex design-and-build project. Stakeholder involvement and influence have been significant since the project's inception. Under such circumstances, the monitoring the stakeholder engagement should be: Performed by the project sponsor A discrete process repeated at monthly intervals Performed by a person external to the project A continuous process