Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data:
Total machine-hours | 31,000 | |
Total fixed manufacturing overhead cost | $ | 310,000 |
Variable manufacturing overhead per machine-hour | $ | 4.00 |
Recently, Job T687 was completed with the following characteristics:
Number of units in the job | 10 | |
Total machine-hours | 30 | |
Direct materials | $ | 730 |
Direct labor cost | $ | 1,460 |
The unit product cost for Job T687 is closest to: (Round your intermediate calculations to 2 decimal places.)
Multiple Choice
-
$115.00
-
$87.00
-
$219.00
-
$261.00
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started