LWH3 Inc. entered into a contract to install a pipeline for a fixed price of $2,200,000. LWH3 recognizes revenue upon contract completion. (Show computations) Cost
LWH3 Inc. entered into a contract to install a pipeline for a fixed price of $2,200,000. LWH3 recognizes revenue upon contract completion. (Show computations)
| Cost incurred | Estimated Cost to Complete | ||||
2017 | $ | 250,000 |
| $ | 1,550,000 |
|
2018 |
| 1,600,000 |
|
| 500,000 |
|
2019 |
| 450,000 |
|
| 0 |
|
In 2019, LWH3 would report gross profit (loss) of: