Machine Hours Overhead 1st quarter (0.1 per unit) 27,000 Costs 560,000 2nd quarter 41,000 780,000 3rd quarter
Fantastic news! We've Found the answer you've been seeking!
Question:
| Machine Hours | Overhead |
1st quarter | (0.1 per unit) 27,000 | Costs 560,000 |
2nd quarter | 41,000 | 780,000 |
3rd quarter | 52,000 | 820,000 |
4th quarter | 37,000 | 450,000 |
The expected units to be produced is 2,000,000 in 2021.
- Using the high-low method method, how much is the estimated overhead cost for 2021?
a.) | 2,457,000 |
b.) | 2,334,100 |
c.) | 2,359,200 |
d.) | 3,196,800 |