Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3 -year
Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3 -year MACRS method to depreciate the machine, and management thinks the machine would have a value of $33,000 at the end of its 5 -year operating life. The applicable depreciation rates are 33.33%,44.45%,14.81%, and 7.41%. Working capital would increase by $35,000 initially, but it would be recovered at the end of the project's 5 -year life. Madison's marginal tax rate is 25%, and an 11% cost of capital is appropriate for the project. a. Calculate the project's NPV, IRR, MIRR, and payback. Do not round intermediate calculations. Round the monetary value to the nearest dollar and percentage values and payback to two decimal places. Negative values, if any, should be indicated by a minus sign. NPV: $ IRR:MIRR:Payback:%%years b. Assume management is unsure about the $110,000 cost savings - this figure could deviate by as much as plus or minus 20%. Do not round intermediate calculations. Round your answers to the nearest dollar. Negative values, if any, should be indicated by a minus sign. Calculate the NPV if cost savings value deviate by plus 20%. $ Calculate the NPV if cost savings value deviate by minus 20%. $ c. Suppose the CFO wants you to do a scenario analysis with different values for the cost savings, the machine's salvage value, and the working capital (WC) requirement. She asks you to use the following probabilities and values in the scenario analysis: Calculate the project's expected NPV, its standard deviation, and its coefficient of variation. Do not round intermediate calculations. Round the monetary values to the nearest dollar and a coefficient of variation to two decimal places. Negative values, if any, should be indicated by a minus sign. The project's expected NPV: $ Standard deviation: $ Coefficient of variation: Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3 -year MACRS method to depreciate the machine, and management thinks the machine would have a value of $33,000 at the end of its 5 -year operating life. The applicable depreciation rates are 33.33%,44.45%,14.81%, and 7.41%. Working capital would increase by $35,000 initially, but it would be recovered at the end of the project's 5 -year life. Madison's marginal tax rate is 25%, and an 11% cost of capital is appropriate for the project. a. Calculate the project's NPV, IRR, MIRR, and payback. Do not round intermediate calculations. Round the monetary value to the nearest dollar and percentage values and payback to two decimal places. Negative values, if any, should be indicated by a minus sign. NPV: $ IRR:MIRR:Payback:%%years b. Assume management is unsure about the $110,000 cost savings - this figure could deviate by as much as plus or minus 20%. Do not round intermediate calculations. Round your answers to the nearest dollar. Negative values, if any, should be indicated by a minus sign. Calculate the NPV if cost savings value deviate by plus 20%. $ Calculate the NPV if cost savings value deviate by minus 20%. $ c. Suppose the CFO wants you to do a scenario analysis with different values for the cost savings, the machine's salvage value, and the working capital (WC) requirement. She asks you to use the following probabilities and values in the scenario analysis: Calculate the project's expected NPV, its standard deviation, and its coefficient of variation. Do not round intermediate calculations. Round the monetary values to the nearest dollar and a coefficient of variation to two decimal places. Negative values, if any, should be indicated by a minus sign. The project's expected NPV: $ Standard deviation: $ Coefficient of variation
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started