Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long term construction contracts..... They were working on a contract

Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long term construction contracts.....

They were working on a contract for which they would receive $900,000 at completion....

In 2024, they reported a gross profit of 58,440.....

2025 was a disastrous year for the company. As of the end of the year, they had incurred costs of $800,000 (which includes costs for both 2024 and 2025) , and think it is going to cost 120,266 to finish the project.

How much of a loss should they report in 2025? (Enter the loss as a positive number...Example: loss of "150,000".)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Stacey Whitecotton, Robert Libby, Fred Phillips

3rd edition

77826485, 978-0077722074, 77722078, 978-0077826482

Students also viewed these Accounting questions