Question
Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number
Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed.
Setup cost | $20 |
Annual holding cost | $220 per mainshaft |
Daily production | 360 mainshafts/day |
Annual usage | 25,000 (50 weeks5 days eachdaily usage of 100 mainshafts) |
Lead time | 3 days |
Safety stock | 0.50 days' production |
Part 2Kanban container size = _________
mainshafts (round your response to the nearest whole number).
Part 3Number of kanbans = ____________
kanbans (round your response to the nearest whole number).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started