Question
1 Approved Answer
Maintenance costs at Seaside Manufacturing over the past six months are listed in the following table. Maintenance Machine Month cost hours January $13,600 15,500
Maintenance costs at Seaside Manufacturing over the past six months are listed in the following table. Maintenance Machine Month cost hours January $13,600 15,500 February $14,720 16,900 March $13,000 14,000 April $14,480 16,600 May $16,000 18,000 $13,200 15,000 June Using the high-low method, what would the total maintenance costs be if 17,900 machine hours were used? (Round any intermediary calculations to the nearest cent.) $2575 $31,425 $13,425 $15,925