Maintenance Machine Month cost hours June $5,000 350 July 3,000 320 August 4,000 315 September 3,300 220 Coefficients shown by a regression program are
Maintenance Machine Month cost hours June $5,000 350 July 3,000 320 August 4,000 315 September 3,300 220 Coefficients shown by a regression program are as follows: Intercept X Variable 1 1,000 8.5 Using the results of regression, calculate the fixed cost of maintenance. Oa. $900 Ob. $1,000 Oc. $825 Od. None of these choices are correct.