Question
Make some assessments of the maintenance scheduling of a ship. Use PERT three-estimate approach. You are to identify slack and critical activities in the schedule
Make some assessments of the maintenance scheduling of a ship. Use PERT three-estimate approach. You are to identify slack and critical activities in the schedule using the PERT mean time. Further, you are to determine the date and time to enter the dry-dock so that with a 80 % probability, the vessel can be finished with the maintenance by the 15th of April 2022 at 12:00 UTC. Make necessary assumptions. You should make use of Excel to do the estimates.
Below are the activities that are mapped out for the maintenance to be done on the ship.
Activity | Immediate predecessor | Optimistic estimate | Most likely estimate | Pessimistic estimate |
A | ----- | 1 | 1 | 3 |
B | A | 1 | 2 | 3 |
C | B | 3 | 4 | 6 |
D | B | 1 | 2 | 3 |
E | B | 2 | 3,5 | 8 |
F | C | 1 | 1 | 1 |
G | C | 1 | 1 | 2 |
H | C | 3 | 3 | 4 |
I | F | 1 | 2 | 3 |
J | F | 1 | 3 | 6 |
K | G | 1 | 3 | 4 |
L | G | 3 | 5 | 7 |
M | G | 1 | 2 | 3 |
N | H | 3 | 4 | 6 |
O | DE | 2 | 4 | 5 |
P | D | 3 | 5 | 6 |
Q | I | 2 | 3 | 5 |
R | IJK | 3 | 3 | 4 |
S | L | 2 | 3 | 4 |
T | L | 3 | 3 | 6 |
U | N | 2 | 5 | 9 |
V | N | 2 | 4 | 7 |
W | OP | 3 | 5 | 8 |
X | Q | 4 | 5 | 7 |
Y | RST | 1 | 2 | 3 |
Z | MUV | 3 | 4 | 6 |
*a | W | 2 | 2 | 3 |
*b | W | 1 | 3 | 4 |
*c | OXYZ | 1 | 2 | 3 |
*d | *a *b | 2 | 3 | 5 |
*e | *c | 2 | 3 | 4 |
The activities noted *a, *b are not special activities, and are to be considered as the other activities.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started