Make the Network diagram for one of the examples. Make Critical Path for the same Slack for the Task G And J Task Name Duration
- Make the Network diagram for one of the examples.
- Make Critical Path for the same
- Slack for the Task G And J
Task Name | Duration (Days) | Predecessor |
A | 5 | - |
B | 4 | A |
C | 3 | B |
D | 2 | A, C |
E | 1 | D, B |
F | 1 | D |
G | 7 | E |
H | 8 | G |
I | 5 | G, F |
J | 4 | I |
K | 3 | H, J |
L | 3 | K |