Make up Pricing and Installation spreadsheets before they are due to be submitted under Network Design Equipment list Equipment and Components Required Part Manufacturer Description
Make up Pricing and Installation spreadsheets before they are due to be submitted under Network Design Equipment list Equipment and Components Required Part Manufacturer Description Cost Per Quantity Total RouterFirewallWAP etc Only needed if ISP modem is bridge only each WAP Secondary WAP should come with PoE injector kit each each each each each Pck each each each each each each each each Pck Sub total parts State Tax Total Parts Labor Application Description Cost Per Quantity Total Cable Installation Pull Rack installation hour Total Labor Total Cost Total Proposal Recurring Expence Service Vendor Name Manufacturer Description Cost Unit Quantity Total Month Month Timeline On Site Start Date through End Date May The date you intend to start ordering goes here in the yellow Preliminary walkthrough May Hardware Cost Received This is when you got the contract back Order Parts Cat a wire You order the parts that will be installed first Patch Panel Rack Wall Plates Wall Jacks J Hooks cat a patch Cableft cat a patch Cableft Parts Delivered Wire Installation Pull wire Install and troubleshooting takes about days Terminate Boxes Order Parts Switch We order the expensive parts last so we don't UPS have to leave them on the work site where they Power Bar could get stolen and only install them after we Parts Delivered have tested the wiring Rack Installation Mounting Rack Here we install the rack and its components in one day Add Patch Panel to Rack Punch Down Rack Add Rack Components Testing This is all follow up things before final acceptance Walk Through PunchList Start Final Walkthrough Complete
Make up Pricing and Installation spreadsheets before they are due to be submitted under Network Design Equipment list
Equipment and Components Required
Part Manufacturer Description Cost Per Quantity Total
RouterFirewallWAP etc Only needed if ISP modem is bridge only each
WAP Secondary WAP should come with PoE injector kit each
each
each
each
each
Pck
each
each
each
each
each
each
each
each
Pck
Sub total parts
State Tax
Total Parts
Labor
Application Description Cost Per Quantity Total
Cable Installation Pull
Rack installation hour
Total Labor
Total Cost Total Proposal
Recurring Expence
Service Vendor
Name Manufacturer Description Cost Unit Quantity Total
Month
Month
Timeline On Site
Start Date through End Date
May The date you intend to start ordering goes here in the yellow
Preliminary walkthrough May
Hardware Cost Received This is when you got the contract back
Order Parts
Cat a wire You order the parts that will be installed first
Patch Panel
Rack
Wall Plates
Wall Jacks
J Hooks
cat a patch Cableft
cat a patch Cableft
Parts Delivered
Wire Installation
Pull wire Install and troubleshooting takes about days
Terminate Boxes
Order Parts
Switch We order the expensive parts last so we don't
UPS have to leave them on the work site where they
Power Bar could get stolen and only install them after we
Parts Delivered have tested the wiring
Rack Installation
Mounting Rack Here we install the rack and its components in one day
Add Patch Panel to Rack
Punch Down Rack
Add Rack Components
Testing This is all follow up things before final acceptance
Walk Through
PunchList Start
Final Walkthrough
Complete
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started