Question

1 Approved Answer

Management of Mittel Company wants to reduce the elapsed time from when a customer places an order to when it is shipped. It provided the

Management of Mittel Company wants to reduce the elapsed time from when a customer places an order to when it is shipped. It provided the following data for a recent quarter:
\table[[Inspection time,0.3 day],[Wait time (from order to, start of production),16.7 days],[Process time,2.6 days],[Move time,0.8 day],[Queue time,4.4 days]]
Required:
Compute the throughput time.
Note: Round your answer to 1 decimal place.
2. Compute the manufacturing cycle efficiency (MCE) for the quarter.
Note: Round your percentage answer to nearest whole percent.
3. What percentage of the throughput time was spent in non-value-added activities?
Note: Round your percentage answer to nearest whole percent.
4. Compute the delivery cycle time.
Note: Round your intermediate calculations and final answer to 1 decimal place.
5. If using Lean Production eliminates all queue time, what will be the new MCE?
Note: Do not round intermediate calculations. Round your percentage answer to 1 decimal place.
\table[[1. Throughput time,days],[2. Manufacturing cycle efficiency,%
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Money And Wealth

Authors: Joslyn Pine

1st Edition

0486486389, 9780486486383

More Books

Students also viewed these Accounting questions