Management of Mittel Company would like to reduce the amount of time between when a customer places on order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time wait time (from order to start of production) Process time Move tine Queue time 0.4 days 15.6 days 2.7 days 0.5 days 4.2 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.) 4. Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.) 5. If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate calculations. Round your percentage answer to 1 decimal place.) 1. Throughput time 2. Manufacturing cycle efficiency 3. Non-value-added throughput time 4. Delivery cycle time 5. New manufacturing cycle efficiency days % % days % Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units. Actual run time this week Machine tine available per week Actual run rate this week Ideal run rate Detect-free output this week Total output this week including defects) 7,020 minutes 9,000 minutes 9.35 units per minute 11.00 units per minute 18,000 unite 20,000 units Required: 1. Compute the utilization rate (Round your answer to 2 decimal places.) 2. Compute the efficiency rate. (Round your answer to 2 decimal places.) 3. Compute the quality rate. (Round your answer to 2 decimal places.) 4. Compute the overall equipment effectiveness (OEE). (Do not round intermediate calculations. Round your final answer to 3 decimal places.) Utilization rate Efficiency rate Quality rate Overall equipment effectiveness