Question
Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when
Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: |
Inspection time | 0.3 | days |
Wait time (from order to start of production) | 14.0 | days |
Process time | 2.7 | days |
Move time | 1.0 | days |
Queue time | 5.0 | days |
Required: | |
1. | Compute the throughput time. ____ days? |
2. | Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) |
Manufactoring cycle effiiency___?
|
3. | What percentage of the throughput time was spent in nonvalue-added activities? |
non value addded troughput time ____%? |
4. | Compute the delivery cycle time. delivery cycle time:___ days |
5. | If by using Lean Production all queue time during production is eliminated, what will be the new MCE?(Enter your answer as decimals rounded to 3 places.) |
new manufactoring efficiency? |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started