Manufacturing bread must be processed through each of the three operations (mix, bake, pack) in sequence. The mixer can mix enough ingredients for 100 loaves

Manufacturing bread must be processed through each of the three operations (mix, bake, pack) in sequence. The mixer can mix enough ingredients for 100 loaves of bread every 15 minutes, the oven is capable of baking 100 loaves of bread every 20 minutes, and the packing machine can handle a batch of 100 loaves of bread

every 12 minutes

Please draw the process flow chart for the process described above. What is the throughput time for a single loaf of bread at this facility?

Which station is the bottleneck, and how much bread is produced by this manufacturing process during a typical 8-hour workday?

C.I

The firm is considering purchasing an additional oven to help with the baking process that would have a capacity like the current oven (100 loaves every 20 minutes). Would buying this machine change the bottle neck for this facility? How about the throughput time for a single load of bread?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Logistics

Authors: Paul R. Murphy, Michael Knemeyer

11th edition

132953463, 2900132953466, 978-0132953467

More Books

Students also viewed these General Management questions

Question

Which of the following statements about Adjusted R 2 is false?

Answered: 1 week ago