Manufacturing Cost information The current material cost for a single brick of products HB 22, HB 27 & HB 29 are $4.00, $5.00 & $6.00
Manufacturing Cost information
The current material cost for a single brick of products HB 22, HB 27 & HB 29 are $4.00, $5.00 & $6.00 respectively. In the most recent analysis, which includes the new products, the average indirect cost was revealed to be about $5.50 per brick.
Pricing
HBIs sets prices based on the product cost. Their markup is set to cover selling and administrative expenses and return a desired level of profit. Because on the new indirect cost information, the price on the HB22 has increased. The current prices have a 50% markup over the cost as present in Exhibit 1.
Decision making for special orders
As long as there is capacity, HBI will be profitable if they the selling price exceeds the cost to produce and ship the order. This would include the manufacturing cost plus 4 % of sales revenue for commissions and sales bonuses.
Complete and submit the following calculations
- Using values provided in the case, calculate 1) the production cost, 2) the normal selling price, and proposed minimum price of each brick type.
- Using a volume-based approach and the cost information for December provided in the exhibits, where each unit of brick is assigned the same costs regardless of the brick type, calculate 1) the production cost, 2) the normal selling price, and proposed minimum price of each brick type.
- Using material cost as the allocation base for conversion costs and the information in the exhibits about December production, calculate 1) the production cost, 2) the normal selling price, and proposed minimum price of each brick type.
- Using an activity-based costing approach and information from the exhibits about December production, calculate 1) the production cost, 2) the normal selling price, and proposed minimum price of each brick type based on the manufacturing activities:
- Use BTU information for assigning fuel cost
- Choose an approach to assign special grinding costs
- Use volume-based costing for other costs.
- Choose an activity base to assign grinding costs.
Make sure to fully show your work !!!!
Exhibit 1 | ||||||
Firebrick Products |
|
|
|
| ||
Product | Temperature (F) | Average BTUs required per Hour | Hours in the oven per 1000 brick | Material Cost per Brick | Total Material Costs | Current Selling Price per Brick |
HB 22 | 2200 | 2,100,000 | 7 | $4 | $28,000 | $14.25 |
HB 27 | 2700 | 2,500,000 | 4.8 | $5 | $20,000 | $15.75 |
HB 29 | 2900 | 3,000,000 | 3 | $6 | $12,000 | $17.25 |
Exhibit 2 |
|
|
|
|
| |
Conversion Costs for December |
| |||||
| Total | Firing | Grinding | Hand Grinding | Other | |
Depreciation | $20,000 | $5,000 | $3,000 | $600 | $11,400 | |
Labor | 10,000 | 1,000 | 0 | 200 | 8,800 | |
Energy (gas) | 30,000 | 15,000 | 1000 | 200 | 13,800 | |
Other | 12,000 | 1,000 | 0 | 0 | 11,000 | |
Total | $72,000 | $22,000 | $4,000 | $1,000 | $45,000 | |
Exhibit 3 |
|
|
|
|
| |
December Customers |
| |||||
Customer | HB 22 | HB 27 | HB 29 | Total Bricks produced and Sold |
| |
Automotive | 1000 | 1000 | 1000 | 3000 |
| |
Bio-technical | 1000 | 0 | 0 | 1000 |
| |
Chemical | 5000 | 1000* | 0 | 6000 |
| |
Diesel | 0 | 2000 | 1000 | 3000 |
| |
Totals | 7000 | 4000 | 2000 | 13000 |
*500 of the HB 27 ordered by chemical also required hand grinding.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started