Marigold has a standard of 2 hours of labor per unit, at $15 per hour. In producing 3800 units, Marigold used 7450 hours of labor
Marigold has a standard of 2 hours of labor per unit, at $15 per hour. In producing 3800 units, Marigold used 7450 hours of labor at a total cost of $113985. Marigold's labor price variance is $350U.$15F.$2295F.$2235U