Question
Mark Gunther and Sony are trying to determine the safety stock ( SS ), Base Stock( S ) and Order Quantity for its circuit cards
-
Mark Gunther and Sony are trying to determine the safety stock (SS), Base Stock(S) and Order Quantity for its circuit cards using a Periodic Review Inventory Management System. It takes 25 days for Sony to receive its cards, i.e., a lead-time of 25 days, and Sony uses a review period (I) of 11 days. Mark estimates that the daily demand for Sony is 250 cards on average with a daily standard deviation of 70 units. After long conversations with the management team, Samsung agrees to target a service level of 91%. The Normal Distribution Table can be found in the Mambo packet.
1) What is the expected demand during the Review Period and Lead Time?
a. None of the answers listed
b. 9,000
c. 4,800
d. 6,250
e. 7,500
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started