Mark is currently working on the workstation upgrade project. He has noticed that there are three activities on the critical path they are activity A,
Mark is currently working on the workstation upgrade project. He has noticed that there are three activities on the critical path they are activity A, C, and D. Activity B has a slack of 2 and a duration of four days. Activity C has a duration of three days and activity D has a duration of six days. What is the slack on activity A