Question
Markup on Cost, Cost-Based Pricing Arthur Quillen Construction Company is a general contractor that specializes in custom residential housing. Each job requires a bid that
Markup on Cost, Cost-Based Pricing
Arthur Quillen Construction Company is a general contractor that specializes in custom residential housing. Each job requires a bid that includes Quillen's direct costs and subcontractor costs as well as an amount referred to as "overhead and profit." Quillen's bidding policy is to estimate the costs of direct materials, direct labor, and subcontractors' costs. These are totaled, and a markup is applied to cover overhead and profit. In the coming year, the company believes it will be the successful bidder on 10 jobs with the following total revenues and costs:
Revenue$8,740,000Direct materials$2,250,000Direct labor1,900,000Subcontractors3,450,0007,600,000Overhead and profit$1,140,000
Required:
1.Given the preceding information, what is the markup percentage on total direct costs?
%
2.Suppose Quillen is asked to bid on a job with estimated direct costs of $570,000. What is the bid?
$
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Markup percentage on total direct costs Following Quillens bidding policy the total direct costs are the sum of direct materials direct labor and subcontractor costs Total direct costs 2250000 materia...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started