Question
1 Approved Answer
(a) (b) (c) (d) (e) (f) The table below depicts the WBS Dictionary for a software development project: Task Task A Duration (days) Dependency
(a) (b) (c) (d) (e) (f) The table below depicts the WBS Dictionary for a software development project: Task Task A Duration (days) Dependency Resource Worker 1 Worker 1 Worker 2 Task D Worker 2 Task E Worker 3 Task F Worker 2 Task G Worker 1 Using any appropriate technique, calculate the duration of the project. Draw the resource usage graph for Worker 1, Worker 2, Worker 3. Task B Task C 2 3 2 1 2 1 2 A B C,D E F Comment on resource usage in this project and perform any required resource leveling. State any assumptions. State any THREE factors that you would consider when allocating work to different members of a team. The customer would like the project duration to be reduced. State THREE techniques by which individual task durations could be reduced. What are the possible pitfalls of each technique?
Step by Step Solution
★★★★★
3.48 Rating (164 Votes )
There are 3 Steps involved in it
Step: 1
a Using a critical path method we can calculate the duration of the project as follows Task A 2 days Task B 3 days Task C 2 days starts on day 2 Task ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started