Material Requirements Planning (MRP) What number should be placed in the spot presently filled with the X? (Refer to Slides 34 to 37 in Chapter
Material Requirements Planning (MRP) What number should be placed in the spot presently filled with the X? (Refer to Slides 34 to 37 in Chapter 03 -or- Pages 82 through 88 in the textbook) Finished Product B Projected on Hand Inventory Gross Requirements Schedule Receipts Planned Delivery Beginning Inventory = 80 Type your answer... JAN 30 50 FEB 50 100 100 MAR 70 60 X APR 40 50