Fargo Company manufactures products in batches of 100 units per batch. The company uses a standard cost system and prepares budgets that call for 500 of these batches per period. Fixed overhead is $60,000 per period. The standard costs per batch follow:
Material (80 gallons) $32
Labor (60 hours) 480
Factory overhead 252
Standard cost per batch $764
During the period, 503 batches were manufactured, and the following costs were incurred:
Materials used (40,743 gallons) $15,482.34
Labor (29,677 hours at $865 per hour) 256,706.05
Actual variable overhead 67,080.00
Actual fixed overhead 60,500.00
Required:Calculate the variances for materials, labor, and overhead. For overhead, use the two-variance method. ( Please use the information given about budgeted fixed overhead to compute the variable rate.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the variances for materials labor and overhead using the twovariance method we need to follow some structured steps 1 Material Variances ...See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started